Access and structure
Check door openings, turning space, crane or forklift access, floor loading, plinths, anchors, overhead clearance and maintenance withdrawal space.
Site readiness to accepted production
Use a controlled seven-step sequence to receive, position, connect, test and hand over food-processing equipment. Project drawings and the approved technical agreement remain the governing documents for every machine.
Close these four planning packages before delivery. Each item should identify the responsible party and the evidence required for acceptance.
External FAT case demonstration · 1:33
This Thermo Scientific and Snyder’s-Lance case video shows what the written sequence above looks like before shipment: the customer reviews the completed system, runs product, discusses details and records changes that must close before delivery.
The useful evidence is the interaction: agreed checklists guide the day, representative product is run, unresolved details are documented and post-test changes remain visible before shipping. FAT reduces start-up uncertainty but does not replace site readiness, SAT or final product acceptance.
Source and limit: External case video published by KeepingFoodSafe on 19 April 2013 about a Thermo Scientific packaged-product inspection system for Snyder’s-Lance. It is not a HELPER FAT, a universal checklist or proof that factory testing replaces installation, SAT and product acceptance at the buyer’s site.
Open the original video on YouTubeFreeze the installation basis: approved layout, equipment list, connection schedule, delivery route, responsibility matrix and acceptance plan. Do not size a utility from a generic machine category when a model-level drawing is available.
Check door openings, turning space, crane or forklift access, floor loading, plinths, anchors, overhead clearance and maintenance withdrawal space.
Separate raw and finished-product traffic, confirm floor falls and drains, protect clean areas during construction and avoid inaccessible service voids.
Verify voltage, phase, frequency, protective devices, water quality, steam condition, compressed-air quality, exhaust, cooling and wastewater interfaces.
Each stage closes with evidence before the next begins. The exact tests depend on the configured machine and destination-market requirements.
Record both the available supply and the machine requirement. Connection size alone does not prove adequate pressure, flow, quality or peak demand.
| Utility | Confirm before delivery | Evidence at commissioning |
|---|---|---|
| Electrical | Voltage, phase, frequency, installed power, demand, breaker, earthing and enclosure/environment requirement. | Recorded supply, phase sequence, protection settings, motor direction and loaded current. |
| Water | Potable/process status, temperature, pressure, flow, connection, backflow control and peak simultaneous demand. | Flow and pressure under operating demand; leak and cleaning checks. |
| Steam | Pressure at point of use, quality, pipe size, isolation, strainer, trap, condensate return and warm-up allowance. | Stable pressure during load, condensate removal and temperature response. |
| Compressed air | Pressure, normal and peak flow, air quality, dew point, filtration, isolation and local storage. | Pressure at the machine during cycling, leak check and actuator response. |
| Drainage / exhaust | Peak liquid and solids load, floor fall, air volume, discharge route and treatment limits. | No uncontrolled pooling, backflow, excessive vapour or unsafe discharge. |
Boundary: values must come from the approved model-level utility schedule. Online calculators are early planning aids, not final connection data.
Define which evidence belongs at the supplier factory and which can only be demonstrated after installation with the customer's utilities, materials and operators.
Confirm configured equipment, documentation, guarding, controls, no-load functions and agreed test material where practical before shipment.
Confirm installation, site utilities, interlocks, line communication, safe operation and functions that depend on the customer's factory.
Measure accepted output, quality, yield, temperature, changeover and cleaning against agreed raw-material and recipe conditions.
A working machine is not a complete handover. Close the records that operations, sanitation and maintenance will need after the commissioning team leaves.
Commissioning verifies the installed machine, site utilities, safety functions, controls, line communication and agreed product trial before handover. The signed project scope should assign every test and responsible party.
Confirm delivery access, floor and anchors, service clearance, hygienic zoning, drainage and each utility at the point of use. Use approved model-level drawings rather than category estimates.
FAT records agreed checks before shipment at the supplier. SAT confirms the installed system with the customer's actual utilities, interfaces and site conditions.
General planning references: Oklahoma State University food-processing facility design guide, FAO GHP facility and equipment design guidance, and EHEDG guideline catalogue. These sources support general planning only; HELPER project drawings and approved test protocols control the supplied equipment.
Standards & safety pathway
Installation acceptance should use the final machine configuration, sanitation boundary and controlled document register.